The general schedule for design and construction of the pavilion addition is as follows:
 
Schematic design
   
Sustainable Design Charrette #1
    Sustainable Design Charrette #2
August - October 2006
Aug. 30-31, 2006
Sept. 12-13, 2006 
Design development 
November 2006 - January 2007 
Groundbreaking ceremony
Sept. 7, 2007, 3:30 p.m.
Construction bids date
February 28, 2008
Construction begins
Spring 2008
Construction concludes
Spring 2009
Occupy King Pavilion   
May 2009
 